On a construction-linked plan, each instalment becomes payable when a construction milestone is reached. The demand letter is how the buyer learns that the milestone has been reached and what they owe. A clear letter gets paid faster and is your record if the payment is later disputed.
What a demand letter must contain
- Buyer and unit. Name of every allottee as in the agreement, unit number, tower, project name and the project’s RERA registration number.
- Reference to the agreement. Date of the agreement for sale and the clause or schedule that sets out the payment plan.
- The milestone. Which milestone has been reached, and the date it was reached. Attach the architect’s or engineer’s certificate if your agreement provides for one.
- The amount. The instalment as a percentage of the consideration and as a rupee figure, GST shown separately, any other charges due at this stage, less any amount already received, and the net amount payable.
- The due date. The date by which payment must be received, counted as the agreement provides.
- How to pay. The designated project collection account: account name, number, bank, branch and IFSC. Ask the buyer to quote the unit number as the payment reference.
- TDS, where it applies. If the buyer must deduct tax at source on the payment, say so and ask for the challan and certificate.
- Home loan buyers. A line the buyer can forward to their bank for disbursement, with the amount and milestone.
- Interest on delay. The rate of interest that applies after the due date, as set out in the agreement and the applicable RERA rules.
- A statement of account. Total consideration, amount demanded to date, amount received to date, and balance.
- Contact. A named person, phone number and email for queries.
Template
Copy the text below and replace the parts in square brackets.
[Developer name] [Registered office address]
Date: [DD Month YYYY] Demand letter no.: [Number]
To [Name of allottee 1] and [Name of allottee 2] [Correspondence address]
Subject: Demand for instalment due on [milestone] for Unit [number], [Tower], [Project name] (RERA registration no. [number])
Dear [Name],
We refer to the Agreement for Sale dated [date] for the above unit. Under the payment schedule in [Schedule / clause], an instalment falls due when [milestone, for example “the fifth floor slab is cast”].
We are pleased to inform you that this milestone was reached on [date]. The following amount is now payable:
Particulars Amount (₹) Instalment: [x]% of consideration [amount] GST at [rate]% [amount] Other charges due at this stage, if any [amount] Less: amount already received against this instalment [amount] Net amount payable [amount] Please pay the net amount on or before [due date] to:
Account name: [Project collection account name] Account number: [number] · Bank: [bank, branch] · IFSC: [code] Payment reference: [Unit number]
[If applicable: Please deduct tax at source as required under the Income-tax Act and send us the challan and certificate.]
If you have taken a home loan, please forward this letter to your bank for disbursement of ₹[amount] against the above milestone.
Payments received after the due date attract interest at the rate provided in the Agreement for Sale and the applicable RERA rules, from the due date until the date of payment.
Statement of account as on [date]
Amount (₹) Total consideration [amount] Demanded to date, including this demand [amount] Received to date [amount] Balance payable after this demand [amount] For any clarification, please contact [name] on [phone] or [email].
Yours sincerely, For [Developer name] [Authorised signatory]
Have your legal team check the template against your agreement for sale before you use it, particularly the interest clause and the counting of the due date.
A collections workflow that works
A good letter is one step. The workflow around it decides whether money arrives on time.
- Seven days before the milestone: tell buyers the milestone is close, so home loan buyers can alert their bank.
- On the milestone date: issue the demand letter by email and WhatsApp, with the statement of account.
- Three days before the due date: send a reminder to buyers who have not paid.
- On receipt: issue a receipt with the bank reference the same day, and update the buyer’s statement.
- After the due date: move the amount into aging buckets (0–30, 31–60, 61–90, over 90 days) and assign each overdue account to a named person.
- Every Monday: review the aging report by project, and next month’s expected demands.
Doing it without a template
In Jeevak OS, the Collections module tracks each milestone on construction-linked, down-payment and flexi plans, generates the demand letter as a PDF with the buyer’s full payment history, records receipts against bank references, and shows overdue amounts by aging bucket with a six-month forecast.
Related
Anurag leads product and engineering at Jeevak OS. Before starting the company he ran marketing for a Hyderabad real estate developer, where he was responsible for lead generation across residential projects. He splits his time between site offices and the codebase.